Created: Nov 25, 2019 19:33 | Source @OVH

In progress - Amélioration

En avril 2019, nous avons introduit les premières bases de données managées sur du stockage ultra-rapide NVMe.
Nous avons d'abord créé toutes les nouvelles instances SharedSQL, PrivateSQL et CloudDB sur ce nouveau matériel. Puis, nous avons migré les CloudDB (réseau publique). On s'est ensuite occupé de migrer massivement les 800000 SharedSQL et 12000 PrivateSQL du centre de données de P19. Cette migration est désormais terminée, nous entamons maintenant le chantier de migration des derniers PrivateSQL de Gravelines vers ce nouveau matériel. Les derniers SharedSQL ne sauraient tarder.
Les migrations des PrivateSQL de Gravelines, cluster sql001, seront faites ces 6 prochaines semaines. Elles entraîneront une coupure d'une minute environ par instance.
---
In April 2019, we introduced the first managed databases based on ultra-fast NVMe storage.
We first created the new SharedSQL, PrivateSQL and CloudDB instances on this new hardware. Then, we migrated the CloudDB (public network). We then moved massively the 800000 SharedSQL and 12000 PrivateSQL of the P19 datacentre. This migration is now over. We now begin the migration of the last Gravelines' PrivateSQL to this new hardware. The last SharedSQL will follow.
The migration of the PrivateSQL of Gravelines, sql001 cluster, will be done on the next 6 weeks. A 1 minute of downtime is expected per instance.
Comments
The intervention is starting…
Nov 25, 2019 22:30 by OVH
Intervention completed. Next part: tomorrow, from 22:30 CET.
Nov 25, 2019 23:47 by OVH
The intervention is starting…
Nov 26, 2019 22:32 by OVH
About 20% done for tonight. All is going fine…
Nov 26, 2019 23:16 by OVH
Intervention completed. Next part: tomorrow, from 20:30 CET.
Nov 27, 2019 05:25 by OVH
The intervention is starting…
Nov 27, 2019 22:01 by OVH
Intervention completed. Next part: next week.
Nov 27, 2019 22:51 by OVH
The intervention is starting…
Dec 02, 2019 22:31 by OVH
About 20% done for tonight. All is going fine…
Dec 02, 2019 23:42 by OVH
Intervention completed. Next part: on Thursday.
Dec 03, 2019 03:14 by OVH
The intervention is starting… The end is expected at 08:00 CET.
Dec 05, 2019 22:30 by OVH